11
# Roadmap: plann
22

3-
**This document is a draft** - it was generated by Claude Opus 5.0. As of 2026-08-25 significant parts of it has been reviewed and edited by Tobias Brox. In any case, **an estimate is an estimate** - the only way to know for sure how much time a task will take is to actually do it.
3+
**This document is a draft** - it was generated by Claude Opus 5.0. Parts of it has still not been through human scrutiny. In any case, **an estimate is an estimate** - the only way to know for sure how much time a task will take is to actually do it.
44

55
## Funding
66

@@ -35,9 +35,7 @@ task list, the code references and the acceptance criteria, and is kept current
3535
the work proceeds.
3636

3737
This document holds what an issue tracker is bad at: the shape of the whole, why the
38-
hours are distributed the way they are, what depends on what, what gets released
39-
when, and what is deliberately *not* funded. Where this document and an issue
40-
disagree on a detail, the issue wins.
38+
hours are distributed the way they are, what depends on what, and what is deliberately *not* funded. Where this document and an issue disagree on a detail, the issue wins.
4139

4240
Every item has a status: `[x]` done, `[ ] wip` partly done (the text around the
4341
table says what is left), `[ ]` not started. The hours are the estimates as made
@@ -110,7 +108,7 @@ config file.
110108

111109
| Status | Item | Deliverable | h | € | Issue |
112110
|---|---|---|---|---|---|
113-
| [ ] wip | 1.0 Release v1.2.0 | The `[Unreleased]` work finished, [PR #43](https://github.com/pycalendar/plann/pull/43) landed, changelog closed, released to PyPI | 10 | 500 | |
111+
| [x] | 1.0 Release v1.2.0 | The `[Unreleased]` work finished, [PR #43](https://github.com/pycalendar/plann/pull/43) landed, changelog closed, released to PyPI | 10 | 500 | |
114112
| [ ] | 1.1 CalDAV server compatibility | Fixes, or a documented verdict that the fault is `caldav`'s or the server's, with issues filed there | 8 → **4** | 200 | [#25](https://github.com/pycalendar/plann/issues/25), [#26](https://github.com/pycalendar/plann/issues/26) |
115113
| [ ] | 1.2 Multi-calendar mass-edit | Mass-editing that is correct across calendars, or refuses to run when it cannot be | 4 → **3** | 150 | [#48](https://github.com/pycalendar/plann/issues/48) |
116114
| [ ] wip | 1.3 Improving the configuration helper logic | `interactive update-config` resolved one way or the other (it was dropped in v1.2.0 rather than implemented), a `plann configure` without its "here be dragons" warning, and documented non-plaintext credential options | 4 → **3** | 150 | [#49](https://github.com/pycalendar/plann/issues/49) |
@@ -252,28 +250,6 @@ duck.
252250

253251
---
254252

255-
## Release plan
256-
257-
| Release | Contents | After |
258-
|---|---|---|
259-
| 1.2.0 | Code-review fixes, the config-delegation refactor, community patches - the baseline everything else is measured against | 1.0 |
260-
| 1.3.0 | Server-compatibility fixes, multi-calendar fixes, usable configuration | 1.1-1.3 |
261-
| 2.0.0 | calendaring-client backend | Phase 3 |
262-
| 2.1.0 | Time tracking in the calendar, `sum_hours` | 4.1, 4.2 |
263-
| 2.2.0 | Milestone reporting | 4.3 |
264-
| 2.3.0 | Documented, typed, covered | Phases 2, 5 |
265-
266-
The 2.0 number is reserved for the `calendaring-client` migration because that is
267-
where a backward-incompatible change is most likely - and because
268-
[`CHANGELOG.md`](../CHANGELOG.md) commits to "not breaking backward compatibility
269-
unless I really have to (and then under a 2.0-release)".
270-
271-
Note what the reordering costs: the migration now gates every release after 1.3.0.
272-
If Phase 3 slips (see Risks), Phases 2 and 5 still ship - as 1.4.0 - but time
273-
tracking and reporting do not ship at all.
274-
275-
---
276-
277253
## Effort summary
278254

279255
Per-item hours are in the phase tables above.
@@ -287,141 +263,6 @@ Per-item hours are in the phase tables above.
287263
| 5 - Documentation | 42 | 2100 | 29% |
288264
| **Total** | **144** | **7200** | |
289265

290-
### Changes from the original five-bucket plan
291-
292-
The original plan was 156 hours (7800 EUR). It is now **144 hours (7200 EUR)**: 600
293-
EUR was moved to the `calendaring-client` grant to fund the library work that 1.3 and
294-
4.1 shed. The total across the two grants is unchanged.
295-
296-
| Original bucket | Was | Now | Why |
297-
|---|---|---|---|
298-
| Bug fixes and downstream improvements | 12 | 20 | Two open user-reported server-compatibility bugs, an unmerged community PR, a multi-calendar data-integrity bug found during this review, and the configuration/credentials path - which is where a new user meets plann and where an advertised command raises `NotImplementedError`. The v1.2.0 release is now charged here too, at 10 hours, which is why the four bug-fixing items are funded at 10 against a 20-hour estimate |
299-
| QA | 48 | 48 | Unchanged in the end, and still the largest bucket by a wide margin: coverage is 50%, there are no type annotations at all, and two of the 88 TODO comments turned out to be unreported bugs. It was briefly raised to 54 before 300 EUR - six hours - moved to the sibling grant |
300-
| Migration to calendaring-client | 16 | 16 | Unchanged in size, but moved ahead of the time-tracking work, which now depends on it. The library-side APIs that plann became a consumer of are funded in the `calendaring-client` grant rather than here. It buys a partial port and a design critique, not a completed migration |
301-
| Milestone reporting | 32 | 18 | The iCalendar representation of "time spent" is library work, not plann's. And the report itself is an export format over an aggregated task list rather than a feature of its own - once the aggregation groups a selection into budget lines and totals each one, the rendering is a template |
302-
| Documentation | 48 | 42 | Six hours moved to Phase 1. Documentation is still the second-largest block |
303-
304-
---
305-
306-
## Risks
307-
308-
### Phase 3 depends on a sibling project that does not exist yet - and now Phase 4 does too
309-
310-
`calendaring-client` currently consists of a README and a roadmap. No code has
311-
been written. Its own funded scope is 248 hours and its CalDAV backend lands at
312-
roughly hour 100 of that plan.
313-
314-
This is the largest scheduling risk in this roadmap. The two projects' estimates
315-
for the same work also disagree: `calendaring-client`'s roadmap budgets 6 hours for
316-
its side of the port while estimating the full migration at 24-40 hours in its
317-
"beyond the funded scope" table.
318-
319-
That disagreement is an artefact of the two plans having been written months apart,
320-
not a structural problem. **Neither roadmap is final, and `calendaring-client` has
321-
not started, so it can still be reprojected** - including moving hours from this
322-
grant to that one where the work turns out to belong there. See the scope note
323-
below.
324-
325-
**This risk grew when time tracking was made to depend on the migration.** The
326-
migration was originally last and load-bearing for nothing; it is now a prerequisite
327-
for all 18 hours of Phase 4. That puts **34 hours - 24% of the grant** behind an
328-
external project that has not yet written a line of code, and it removes the release
329-
valve: dropping the migration now drops time tracking and milestone reporting with
330-
it.
331-
332-
**Mitigation:** Phase 3 is scheduled as early as its dependency allows, and Phases 1,
333-
2 and 5 (110 hours, 76%) are deliberately independent of it, so the grant keeps
334-
delivering while it is blocked. Its own deliverable stays defined as *evidence and a
335-
critique* rather than a finished port, so partial delivery is still delivery.
336-
337-
**Contingency, to be decided rather than discovered:** if `calendaring-client` is not
338-
usable once Phases 1 and 2 are done, Phase 4 is implemented against the `caldav`
339-
library as it stands and ported afterwards. That costs rework, but 4.1's core
340-
question - how to represent time spent in iCalendar - is a data-model decision rather
341-
than a backend one, and the chosen storage format survives the port even when the
342-
plumbing does not. The alternative, waiting, risks the grant ending with neither the
343-
migration nor the feature it now blocks.
344-
345-
### Work shed upstream needs a home in the upstream budget
346-
347-
Two items here concluded that logic belongs in the library rather than in plann:
348-
1.3 (configuration and credentials) and 4.1 (the iCalendar representation of time
349-
spent). That is the right call on the merits - see guiding constraint 2 - but it
350-
moves work rather than removing it, and the receiving budget has to actually have
351-
room for it.
352-
353-
- **Configuration and credentials is already funded upstream.**
354-
`calendaring-client`'s item 1.4 (8 hours) covers config format, discovery, and
355-
"credential handling: keyring integration, and never requiring secrets in
356-
plaintext config". Nothing needs to move; the scope just needs confirming.
357-
- **Time-tracking storage is not.** Only the *research* is funded, inside
358-
`calendaring-client`'s item 0.1, whose task-model survey covers "time estimate and
359-
time spent". There is no implementation line for a time-tracking API, and 4.1
360-
depends on one existing.
361-
362-
**Resolved:** `calendaring-client` has been reprojected, with an explicit
363-
"Time-tracking model and API" item (12 h), funded by moving 600 EUR from this grant.
364-
plann's scope drops from 156 to 144 hours accordingly, and the total across the two
365-
grants is unchanged. The work is the same work; which grant pays for it was an
366-
accounting question rather than a technical one.
367-
368-
The failure mode this avoids is both roadmaps assuming the other is paying - which is
369-
how 4.1 would have ended up blocked on an API nobody had budgeted to write.
370-
371-
### Milestone reporting has an audience of one
372-
373-
Phase 4.3 is 9% of the funded period spent on a feature whose most obvious user is
374-
the author, producing reports for this very grant.
375-
376-
**Mitigation:** the aggregation layer (3.2) is generic and useful on its own, and
377-
the NLnet layout is a template on top of it rather than hard-coded logic. Anyone
378-
who bills by the hour gets the same feature. If it turns out otherwise, the item
379-
is at least self-evaluating: the milestone reports for this grant are produced with
380-
it, so a failure is visible immediately rather than at the end.
381-
382-
### Time tracking rests on a standard that does not support it
383-
384-
[`NEXT_LEVEL.md`](../NEXT_LEVEL.md) is explicit that iCalendar has no place to
385-
record time spent: a VJOURNAL cannot carry a DURATION, and the three candidate
386-
workarounds (an illegal DTEND on a journal, `PARTSTAT=X-ATTENDED`, or a new
387-
`VTIMESPENT` component) are all compromises. Whatever Phase 4 picks, other
388-
calendaring tools will not understand it.
389-
390-
**Mitigation:** the representation is documented (3.1) so that it is at least
391-
*legible* to another implementation, and the `timewarrior` export path is kept so
392-
users who need interoperable time tracking have somewhere to go. This is a known
393-
gap in the standards, not a defect in plann, and saying so plainly in the
394-
documentation is part of the deliverable.
395-
396-
### The QA phase has no visible output
397-
398-
Forty-six hours of tests, annotations and TODO triage produce nothing a user can
399-
see. It is the item most likely to be cut when time runs short, and the item whose
400-
absence caused the fifteen correctness bugs that Phase 1 is releasing fixes for.
401-
402-
**Mitigation:** it is scheduled early, its deliverables are numeric (coverage
403-
thresholds, mypy in CI, TODO counts) rather than subjective, and CI enforcement
404-
means the gains cannot silently erode afterwards.
405-
406-
### Maintainer bandwidth
407-
408-
The primary maintainer has several packages to juggle - several of them NLnet-funded -
409-
as well as other priorities and concerns in life. It is a real risk that time will
410-
run out before the allocated funds do.
411-
412-
**Mitigation:** Phases 1, 2 and 5 are independent of everything else,
413-
so partial delivery is meaningful in any order. Phase 1 alone leaves users better
414-
off than today. There are other developers in the pycal pool who may pick up
415-
pieces.
416-
417-
### Peer review is a dependency on other people
418-
419-
Phase 5.5 requires reviewers who are not the author, and the most valuable reviewer
420-
is someone who has never used plann.
421-
422-
**Mitigation:** approach reviewers during Phase 1, not when the documentation is
423-
ready.
424-
425266
---
426267

427268